Construction may be complete, but a data center still needs its building enclosure to meet project performance requirements during operation.

For facilities designed to operate around the clock, problems with water intrusion, air leakage, temperature control, or equipment performance can become difficult and expensive to correct once operations begin.

Commissioning provides a process for confirming performance. It begins during the design phase and continues through construction, testing, and turnover. Unlike commissioning of other systems, where testing occurs toward the end of construction, building enclosure testing occurs throughout construction to ensure that the installed systems meet project requirements. 

Commissioning the Building Enclosure

The building enclosure protects the data center’s controlled interior from outdoor conditions. Water intrusion, uncontrolled air leakage, condensation, and thermal performance problems can affect interior temperature and humidity, placing additional demands on cooling systems, while also damaging equipment and disrupting service.

Building enclosure commissioning (BECx) assesses whether the enclosure's design and installed performance meet the owner's project requirements (OPR). ASTM E2813 establishes fundamental and enhanced levels of BECx, while ASTM E2947 provides guidance on implementing the process.

Depending on project requirements, primary tasks of BECx may include design document reviews, development of a complete enclosure performance testing plan, submittal reviews, site visits to review mockups and overall construction, field performance testing, and project close-out.

Air infiltration and water penetration testing can identify deficiencies in various components, as well as at the interfaces between them. Performing field evaluations while assemblies remain accessible gives contractors an opportunity to investigate and correct problems before interior finishes and equipment are installed, which would make subsequent repairs more disruptive. Unlike mechanical systems, building enclosure systems cannot be “tweaked and balanced,” so proper installation from the start is important.

Preparing for Operational Turnover

Commissioning also prepares facility operators to manage the building after construction.

Turnover documentation may include inspection reports, enclosure testing results, functional performance records, product data, maintenance requirements, and records of corrected deficiencies.

Facility personnel should understand normal operating procedures, maintenance requirements, and how to respond to failures in the building enclosure. Participation in testing and training allows operators to become familiar with the systems they will maintain.

The completed documentation provides a reference for future maintenance, troubleshooting, and facility modifications.

Intertek's Role in Data Center Commissioning and Construction Services

Intertek supports data center projects through building enclosure commissioning and functional performance testing, construction materials testing, special inspections, and other technical services.

These services help owners and contractors identify deficiencies, document construction quality, and verify building performance before turnover.

Although construction materials testing and special inspections are separate from commissioning, their results help owners identify unresolved issues before the facility enters service.

Eric Seaverson headshot
Eric J. Seaverson, P.E.

Senior Director, Central and West Regions, Intertek Building & Construction

Eric has more than 30 years of experience focused on building enclosure consulting, commissioning, and testing. He oversees building sciences operations in the Central, Mountain, and West regions of the U.S., providing technical oversight of new and existing building enclosure projects, including, commissioning, consulting, diagnostic investigations, and design work.